New Construction Project Update – Dec. 2022
There continues to be a lot of activity at CityLink’s facilities on NE Jefferson in the past month! The latest updates from the new paint/body shop (Phase A) and the new maintenance and administrative facilities (Phase B) construction project for CityLink, are below.
Phase A – Rear Building (Paint/Body Shop):
- Punch List – 99% complete
- Close Out Documents – 99% complete from subcontractor
- Design team reviewing
- Owner Training for compressor
- Start up training completed
- Scheduling overall training with CityLink
- Currently 99% complete on Phase A
Phases B, C, & D:
- ANJ Electric
- Backfilled duct bank east of garage
- Formed & poured CT cabinet & transformer pads
- JJB Masonry
- Installed concrete masonary units (CMU) at the elevator shaft #2, garage, and stairwell in the garage
- Hanley (United Ironworkers)
- Erecting the three-story building and garage building steel
- Last beam was officially placed on Dec. 9
- River City Construction (RCC)
- Installed temporary doors at wash bay & garage
- Overhead doors installed in temporary tent structure
- Currently 29.77% complete on Phases B, C, & D
You will find updated photos below that were taken over the past several weeks. A new time-lapse that was taken between November 14, 2022 and and December 7, 2022 is also available below.